I/S Vestforbrænding hereby calls for tenders to build a flue gas condenser unit combined with a compression heat pump unit
to be located at Vestforbrænding, Ejby Mosevej 219, 2600 Glostrup, Denmark, as a part of a carbon capture project. I/S Vestforbrænding
wishes to engage a contractor for the engineering, installation, and commissioning of the combined flue gas condenser and
heat pump unit for boiler lin...
I/S Vestforbrænding hereby calls for tenders to build a flue gas condenser unit combined with a compression heat pump unit
to be located at Vestforbrænding, Ejby Mosevej 219, 2600 Glostrup, Denmark, as a part of a carbon capture project. I/S Vestforbrænding
wishes to engage a contractor for the engineering, installation, and commissioning of the combined flue gas condenser and
heat pump unit for boiler line 5.The combined flue gas condenser and heat pump unit will be implemented to guarantee that
the flue gas temperature does not exceed 30 °C at the flue gas condensation outlet before entering a future carbon capture
plant. The existing flue gas condenser and absorption heat pump must be decommissioned.On the cold side, the heat pump unit
will be cooling an intermediate circuit, while on the hot side, it will be preheating district heating water before entering
the turbine condensers.The scope of the contract comprises detailed design, delivery, installation, testing, and commissioning
of a complet flue gas condenser unit combined with a heat pump unit for boiler line 5.Furthermore, the contract includes an
option for a two-year service contract.